Guide
Time distance charts for linear construction
The whole programme on one drawing of the route, so you can see who is where, which way they are heading and where they will meet.
Not the school graph
Distance across, time down
Search for a time distance chart and most of what comes back is the distance-time graph from school physics. The construction version is related, but you read it differently. Distance is the chainage along the job, across the page. Time runs down. Each activity sits on the stretch of route it works on, so one sloping line is one crew advancing along the alignment, and the flatter the line, the faster the crew.
Why rail, road and pipeline jobs use it
Linear jobs are long and narrow. Access comes from the ends or from a few points along the way, crews follow each other in a set order, and two crews cannot work the same few hundred metres at the same time. A Gantt chart has nowhere to show any of that.
A time distance chart shows it in one picture, which is why these charts turn up in tenders, in monthly reports and on the site office wall. A client's reviewer can check the staging without reading the activity list, and a superintendent can find next month's work fronts by running a finger down from the chainage they care about. If the chart is new to you, start with how to read a time location chart; it is the same drawing under another name.
What planners check on it
- Two kinds of work in the same place at the same time show up as lines that cross, or a line that runs into a block. In TCC the clash check draws a red box round each one.
- A crew programmed in two areas at once shows up as soon as the areas sit side by side on one time scale. In the demo below, drainage is programmed in CENTRAL and WEST at the same time from 18 August to 3 September 2027, and the clash check boxes each overlap in red.
- A road closure is a zone, a stretch of route between two dates. Mark it on the chart and you can see which work falls inside it.
- Shade the wet season or the Christmas shutdown across the chart and you can see which trenching or earthworks land in them.
- With the baseline drawn as dashed grey lines under the current update, every delay becomes a gap you can measure.
Several areas, one time scale
Real jobs are rarely one line. The demo rail project has a main line on one chainage from CH 0 to CH 6,000, split into five areas (WEST, Station B, CENTRAL, the creek bridge and EAST), and a depot on its own chainage from CH 0 to CH 900. The chart at the top of this page sets the five main-line areas side by side on one time scale with one legend, so you can follow a crew from one area to the next: the track crew lays CH 0 to CH 6,000 between 14 February and 8 September 2028, through Station B and over the bridge. When an area has to be issued as its own drawing, TCC prints areas on separate sheets that share one time scale, so the same date sits at the same height on every sheet. The use cases page shows the depot on a sheet of its own.
From an XER to a time distance chart
An XER export from Primavera P6 carries the activities, their dates, the WBS, activity codes and user-defined fields. That is enough to draw the chart, as long as each activity's location is held in one of those fields.
- In P6, give each activity on the route its chainage: a text UDF such as
CH1550-CH1600, or two number UDFs for the start and finish. Separate more than one stretch with semicolons. - Export the project to XER.
- In TCC, open the XER, choose the chainage field and the work type field, and check the validation report before you apply it.
- Set the paper, title block and logos, then export an A3 or A4 PDF.
The XER is opened read-only and nothing goes back to P6. Save the workspace, and when the programme changes, Refresh reads the file again and keeps your mapping, styles and notes. The people you send the chart to do not need P6. The linear scheduling from P6 page goes further into which P6 fields to use and why P6 stays the scheduling tool.
Free download · Version 1.0
Free for everyone
Every feature, with no account and no activation code. Printed sheets carry a small “Made with Time Chainage Chart” line.
Installs in one click and the Store keeps it up to date.
Version 1.0 · 19 MB
If Windows shows “Windows protected your PC”, click More info › Run anyway.
- System
- Windows 10 or 11, 64-bit
- Also needs
- Edge WebView2 and .NET Framework 4.6.2 or later. Most Windows PCs have both.
- Reads
- P6 Professional database, or an XER export
- Internet
- Not needed. The installer version looks for updates once a day; you can turn that off.