How to read a time location chart
Chainage runs across the page and time runs down it. One sloping line is one crew moving along the job.
What it is
A programme drawn along the route
A time location chart, also called a time-location diagram or a time chainage chart, plots every activity against where the work happens and when. Location runs across the page as chainage, the distance along the alignment from a fixed zero. Time runs down, so the start of the job is at the top.
Why linear jobs use it
On a railway, a road, a pipeline, a tunnel or a transmission line, most of the work is a few operations repeated along a long, narrow site. A Gantt chart lists those activities one per row. It tells you when each one happens but not where, so two crews heading for the same culvert in the same month can sit pages apart in the printout and nobody notices.
A time location chart puts the location back. People on a linear job already think in chainage, so each can find their own stretch and read straight down it.
How to read it
Start with the axes. Chainage runs across, usually in metres from CH 0, and dates run down the side. From any point, read across to the side for the date and down to the scale for the chainage. On a job with several areas, each area has its own scale. Here the five areas of the main line continue one chainage from CH 0 to CH 6,000; an area off the line, such as a depot, can start again from its own zero.
- A sloping line is a crew moving along the route. In the sheet above, the track crew (the solid red line) starts at CH 0 in February 2028 and works down and to the right until it reaches CH 6,000 in September.
- The slope is the rate. Because time runs down, a flatter line covers more ground in less time. The track line is flatter than the drainage line above it: track covers the main line between February and September 2028, while drainage runs from June 2027 to March 2028. Short areas such as Station B and the creek bridge are drawn wider than their length and marked with a factor, ×2.1 and ×2.7, so compare slopes only where the scale is the same.
- A line sloping the other way is a crew working back towards CH 0. Earthworks Crew 2, the dashed orange line, starts at the east end near CH 6,000 and works back west, round the creek bridge, to CH 3,000 in CENTRAL, where Crew 1’s line from CH 0 ends.
- A vertical line or bar is work that stays put. The narrow lavender bars in Station B are the station building works, such as STN-1030, in one place through the middle of 2028.
- A block is a stretch of route held for a period. The green block across every area is TR-1010 Trial running and driver familiarisation, which holds the whole line from March 2029 up to MS-1070 Practical completion on 18 April 2029.
- A horizontal line is a single moment across the route. The dashed lines that run through every area, such as MS-1030 Rail delivered to site on 11 February 2028, are key dates.
Then look at the space between the lines. Two lines close together are crews following each other. Two lines that cross, or a line that runs into a block, are two jobs in the same place at the same time: a clash to check, seen by looking rather than by comparing dates in a list.
Other names for the same chart
Depending on the country and the industry, you will hear it called a time-location diagram, a time distance chart, a time chainage chart, a march chart, a linear schedule or a line of balance chart. Our page on time distance charts covers what planners check on the chart, and linear scheduling from P6 covers the data behind it.
Drawing one from a P6 programme
Most linear jobs are already programmed in Primavera P6. P6 knows when each activity happens, but it holds no chainage unless someone gives it one. The usual way is a user-defined field (UDF) on each activity with its location, such as CH1200-CH1800, or two number fields for the start and finish chainage. Then the chart can come from the programme itself instead of being redrawn every month.
Time Chainage Chart (TCC) does this on your own computer. Open an XER export or the local P6 Professional database, choose the field that holds the chainage and the field that holds the work type, and the chart is drawn with a colour and line style for each work type. A range keeps its direction, so CH500-CH300 draws a crew working back towards CH 0. The use cases page shows more of what it can do on the same demo project.
Free download · Version 1.0
Free for everyone
Every feature, with no account and no activation code. Printed sheets carry a small “Made with Time Chainage Chart” line.
Installs in one click and the Store keeps it up to date.
Version 1.0 · 19 MB
If Windows shows “Windows protected your PC”, click More info › Run anyway.
- System
- Windows 10 or 11, 64-bit
- Also needs
- Edge WebView2 and .NET Framework 4.6.2 or later. Most Windows PCs have both.
- Reads
- P6 Professional database, or an XER export
- Internet
- Not needed. The installer version looks for updates once a day; you can turn that off.