Use cases

Time chainage charts from Primavera P6 and XER, for tender and delivery

The same programme, put to work.

Drawn by TCC from a fictional rail project.

Tender programmes

Phases and key dates, above the chart

A bid has to show how the job is staged and when each step falls. Turn on the Phases lane and TCC reads it from the P6 WBS: a bar for each phase with its WBS groups under it, the key dates on top and a time scale along the top as well as the bottom. A marker can close a phase, read from its WBS name or typed in TCC. The chart underneath shows where the work is while it happens.

DRL-DEMO · From notice to proceed to practical completionTime across
TCC showing the demo programme with time running across. Above the chart is the Phases lane: the key dates MS-1010 to MS-1070, and a bar for each phase with its WBS groups: Design and Approvals, Early Works, Civil Works, Track and Systems, and Testing and Commissioning. Two markers close phases, both read from the WBS names: IFC approval on 5 July 2027 and Handover on 18 April 2029, the date of MS-1070 Practical completion. Below the lane, the five areas of the main line are stacked down the side, from WEST at CH 0 to EAST at CH 6,000.
Drawn by TCC, uneditedFictional project
Phases
The WBS level you choose, one colour per phase
Markers and gates
From the WBS name, such as (Gate 2), or typed in TCC
Key dates
Milestones from the WBS you pick, also printed on the sheet
Left column
The phases and their groups, with their months

One line, several areas

A railway is rarely one plain run of track. In this demo the main line runs on one chainage from CH 0 to CH 6,000, split into five areas, and the depot is a site off the line with a chainage of its own from its own zero. Short areas such as Station B and the creek bridge are drawn wider than their length and marked not to scale. TCC sets the areas side by side on one time scale with one legend, so you can follow a crew from one area to the next.

  1. WESTWest sectionCH 0 – 2250

    69 activities. Earthworks Crew 1, drainage and formation in 2027, then track, overhead line and signalling in 2028.

  2. STN-BStation BCH 2250 – 2650

    22 activities, among them the platform walls, footbridge, station building and fit-out. Drawn at ×2.1, not to scale.

  3. BRIDGECreek bridgeCH 4700 – 4950

    12 activities, four of them the bridge itself. Drawn at ×2.7, not to scale. Earthworks Crew 2 works round it.

  4. DEPOTDepotCH 0 – 900

    A site off the main line, on its own chainage: 35 activities, from clearing to systems testing.

Issue one area as its own drawing

In the Sheet panel you tick which areas go on which sheet. Here the five main-line areas share Sheet 1 and the depot has Sheet 2 to itself. Each sheet prints as its own A3 page, with the title block, legend and notes.

Area code
From a P6 activity field, or assigned in TCC
ALL
Activities coded ALL (or FULL) run across every area, as the key dates and trial running do here
Plan strip
Optional: your plan above each area, registered to its chainage. This demo has none.
The depot alone on its own A3 sheet, Sheet 2 of 2, on its own chainage from CH 0 to CH 900: site establishment and clearing in July and August 2027, two Earthworks Crew 2 passes, yard services, the maintenance shed, wash plant and admin building, the stabling roads and turnouts, depot overhead line and signalling, roads and car park, then systems testing and trial running, with the title block and legend.
DEPOT · Depot · Sheet 2 · A3

Baseline comparison

The baseline, drawn under the new dates

Load the contract programme, a tender XER or a P6 baseline project. Activities pair by Activity ID and the baseline draws as a dashed grey line at the same chainage, so every move shows as a gap. An activity pushed into the wet season, the Christmas shutdown or a named period gets a red halo. Drag the line.

DRL-DEMO · March update against the February baselineDrag to compare
Time chainage chart of the March update, Sheet 1: WEST, Station B, CENTRAL, the creek bridge and EAST side by side, with track, overhead line and signalling in 2028.
The same chart with the February baseline drawn as dashed grey lines under the activities. Track, overhead line and signalling now sit about a month below their baseline lines; drainage and formation in WEST and CENTRAL sit slightly above theirs, earlier. Track at Station B · +33 days
Update only With baseline
Drawn by TCC, notes addedFictional project
Against baseline
80 later · 82 earlier
Largest finish slip
49 days
Practical completion
30 days later

Here the March update moves the track and systems work about a month later. Rail is now delivered to site on 11 February 2028 instead of 13 January 2028, and MS-1030 Rail delivered to site is on the critical path, so track, overhead line, signalling, testing and practical completion all follow. The drainage crew is quicker, so drainage and formation finish earlier. Four activities move into the Christmas shutdown, among them DEP-1150 Depot roads and car park, now 49 days later. The report beside the chart lists start and finish variance in calendar days. Filter it to later, earlier, newly shaded, new or removed, click a row to find it on the chart, and export it to CSV.

P6 Planned dates are not a baseline: they move with every reschedule until an activity starts. TCC keeps the accepted programme in the workspace and compares against that.

The baseline comparison report against the February update, data date 2027-02-01: 80 later, 82 earlier, 4 newly in a shaded period, 2 new, 0 removed, 100 unchanged, largest finish slip 49 days, then a table sorted by finish variance with DEP-1150 Depot roads and car park first at 49 days later, newly in the Christmas shutdown.

Crew clash check

Double-booked crews, boxed in red

A crew can only be in one place. When the same work type is programmed in two areas at the same time, TCC draws a red dashed box round each overlap and lists the clash with its dates. Work that is not a crew moving between places, such as plant trades or approvals, can be marked Not a crew on site and is left out. Click a line in the list and its activities are selected on the chart. Nothing is rescheduled for you: it tells you where to look.

DRL-DEMO · Both sheets side by side, crew and spatial checksDrag to compare
Both sheets of the demo drawn as one time chainage chart: the five main-line areas and the depot side by side on one time axis. In several places the same work type runs in two areas at once; nothing on the chart shows it.
The same chart with the clash checks on: red dashed boxes round drainage in WEST while the culverts DR-1020 in CENTRAL and DR-1030 in EAST are programmed, in August and September 2027; round the Station B platform walls and the creek bridge from November 2027 to January 2028; and round the Station B building and the depot admin building in June and July 2028. A solid red ring marks the depot wash plant, programmed in the same place as the cable ducts from April 2028. 1 1 2 2 3 3 4 4 5
Without the check Clash check on
Drawn by TCC, notes addedFictional project
Crew clashes
4 found
Same place, same time
1 place
From list to chart
1 click

Here drainage is programmed in CENTRAL and WEST at the same time from 18 August to 3 September 2027: the culvert DR-1020 Cross culvert CH3420 in CENTRAL, while the drainage crew is still working through WEST. Nothing on the plain chart points to it. The check marks it 1. The culvert added in March, DR-1030 Additional cross culvert CH5380 in EAST, overlaps the crew in WEST from 8 to 22 September (2). One structures crew is booked on the creek bridge and the Station B platform walls from 8 November 2027 to 25 January 2028 (3), and one buildings crew on the Station B building and the depot admin and crew building from 27 June to 31 July 2028 (4). TCC treats a work type as a crew, so you tell it which are not, and the check flags only work that has to move. A solid red ring marks a different problem: two work types in one place at one time. In the depot, DEP-1130 Wash plant building and DEP-1540 Cable ducts and pits are programmed on the same ground from 6 April 2028 (5).

TCC’s Checks list with five findings: Drainage in CENTRAL and WEST at the same time, 18 Aug 2027 to 3 Sep 2027, 5 activities; Drainage in EAST and WEST, 8 to 22 Sep 2027; Civil / Structural in BRIDGE and STN-B, 8 Nov 2027 to 25 Jan 2028; Buildings in DEPOT and STN-B, 27 Jun to 31 Jul 2028; and Buildings and Yard Services in the same place at the same time from 6 Apr 2028.

Programme view

The P6 programme, beside the chart

One button switches the chart to the programme as P6 lays it out: WBS bands, Activity ID, durations, start, finish and total float, with a Gantt beside it. Click an activity to see its predecessors and successors and which one drives it. Right-click it to find it on the time chainage chart, and back again. The people you send it to do not need P6.

TCC’s programme view of the demo programme, critical activities only: WBS bands for Early Works, Procurement, Track and Systems and Track, original and remaining duration, start, finish, total float, location code and work type, a Gantt by quarter, and TK-1090 Track CH2250-CH2400 selected with its four predecessors and two successors listed below.
Activities checked against P6
4,263
Real programmes
4
Differences
0

Every start, finish, duration and float was compared with the P6 database itself. TCC shows days the way P6 does: whole days by default, or one or two decimals to match your P6 setting.

P6 calculates the dates and float. TCC shows them as P6 stored them and never reschedules.

Search
Activity ID and name in one box, every match highlighted
Columns
Choose, order and size them; kept with the workspace
Logic
Predecessors and successors with type, lag, driving and float
Print
The programme to PDF, WBS bands and Gantt included

Try it on your own programme

New to the chart itself? Read how to read a time location chart, then how to set up linear scheduling from P6 and a time distance chart from an XER.

Download free

Questions

How do separable portions share one sheet?

Each portion keeps its own chainage scale, and TCC sets the portions side by side on one time scale with one legend. In this demo the track crew can be followed from WEST through Station B and CENTRAL to EAST on one sheet. Any area can also go on a sheet of its own, as the depot does in this demo.

How does the baseline comparison match activities?

By Activity ID, against the contract programme, a tender XER or a P6 baseline project kept in the workspace. The baseline draws dashed grey at the same chainage; the report gives start and finish variance in calendar days and exports to CSV.

What counts as a crew clash?

The same work type programmed in two areas at the same time — for example Drainage in CENTRAL and WEST from 18 August to 3 September 2027. TCC treats a work type as a crew; work types that are not crews moving between places, such as plant trades or approvals, can be marked Not a crew on site and are left out. TCC boxes each overlap in red, lists it with dates, and selects the activities on the chart when you click the list. It does not reschedule anything.

Do I need P6 to read the programme view?

No. The programme view shows WBS bands, durations, dates, float and logic without a P6 licence, and the people you send the chart to need nothing installed beyond what you send them.

Where do tender stages and gates come from?

From the P6 WBS level you choose: one bar per stage, gates from the stage name or typed in TCC, key dates from the milestones in the WBS you pick.